Karratha Government Office

About This Project

Project Overview

This project was for the co-location of 10 government agencies into a new shared facility in Karratha. This project was completed in a short time fame, with little client inspection due to the remote location.

With multiple agencies within each floor, acoustics were important due to confidential meetings in the shared spaces. Within the meeting rooms complex presentation and video conferencing facilities were installed.

A high level security system was installed as the office location includes multiple public facing areas requiring CCTV, access control and physical security. The acoustic treatments and isolation all passed engineering testing first time.

PROJECT VALUE: $3m – $5m
PROJECT DURATION: 12 weeks
PROJECT SIZE: 2,200sqm

The right way

Freighting materials from Perth up to Karratha required careful planning to ensure they arrived within the programmed time frame. By identifying these items early within the project, no delays were incurred.